Lido Complex (Lido Elementary and LBMS): Phase 3 of the traffic reconfiguration work is underway. Routing of the main entrance is being reconfigured to utilize the traffic signal presently serving Lido Golf Course. The new entrance to Lido Complex will pass through the Lido Golf Course paved area and enter the school grounds just north of the Administration building. Existing utility lines are in the process of being relocated to a taller pole provided and installed by PSEG.

In Lido Elementary a new hot water boiler has been installed and control wiring is being completed. One existing steam boiler is being worked on due to leaky tubes. That boiler will be ready for steaming 12/20/21 or sooner. A temporary boiler is in place to provide steam while the permanent boilers are being prepared for service.

LBHS: Temporary construction fencing is in place around the new asphalt future basketball courts and tidal pond. Concrete and asphalt have been completed for the new courts. The new basketball courts are awaiting delivery of the basketball goals, which are on back order. The painting of the courts will be done in warmer weather. A permeable paver walkway has been completed around the tidal pond and new pond perimeter 4’ high fencing to be installed is on back order. Concrete curb edging and ramps to the gym doors has been completed.

East Elementary: The new crawlspace ventilation system wiring to future fans and dampers has been completed. Final connections and control wiring will be completed after installation of new fans and dampers, (on order). Masonry work is partially completed.

A new steel reinforced wood guardrail has been ordered to protect the south playground from cars in the nearby intersection and will be completed before Jan. 14, 2022.