Summer Construction Project Update: September 8th, 2021

Lido Complex (Lido Elementary and LBMS): Phase 1 of traffic reconfiguration work in the south parking area will be complete today. New concrete islands, walkways, curbs, resurfaced asphalt and road markings have all been installed. Parking may resume in the south lot Thurs., Sept.9. The new parking area at the Administration Building is receiving the concrete curb work this week and asphalt paving should be complete by Sept. 17th. Landscaping will follow.

In Lido Elementary one failed boiler has been removed. A new concrete housekeeping pad has been installed for placement of a new boiler. However, delivery of the new boiler is delayed due to supply chain slowdowns.

LBMS: The surfacing material for the tennis courts was delivered Aug. 26 and work was begun Aug. 30. Because of a shortage in the colored turf for court lines the work will not be complete until Sept. 17th. Most of the work is within the confines of the court’s fencing so it has minimal effect on outside activity. However, there is some periodic staging of material adjacent to the courts and if additional parking is needed the grass near the temp entrance may be utilized. Cars should face the building from the north side of the road loop.

LBHS: Temporary fencing has been removed. The roadway repair and drainage work on the north roadway is complete. The bulkhead fencing and new sidewalk along the bulkhead will be completed by Sept. 10th and parking will resume on the north roadway September 11. A broken storm sewer pipe has been replaced in the bus lane on the south side of the building and has resolved the rainwater flooding issue that has been occurring for years.

East Elementary: Insulation and spray-on fireproofing is complete in the crawl space. The ventilation system to be installed needed to be redesigned due to field conditions. Details on fans, ductwork and exterior louvers are being reviewed.
Lindell Elementary: A new handicap ramp has been installed on the south side of the building. The handrails were installed September 4th and the ramp is ready for use.
A new playground structure has been installed in the north playground area with a rubberized floor surface to match the adjacent playground floor surface.

Nike Site: BOCES has accepted the new classroom and facility for the Medical Assistant Certification program which will begin at the start of school, Sept. 9th.