Phase 3B - Lido Complex [LCX]

Project Phase Description:
• LCX restroom renovations, door and hardware replacement, phone and public address system upgrades, security improvements, ADA compliance upgrades, mechanical, electrical, and plumbing upgrades including boiler replacement and ventilation upgrades

Current Project Stage: Construction Documentation in progress, scheduled for completion end of May 2010
• SED preliminary submission by June 2010

Subsequent Project Stages:
• SED approval anticipated in September 2010
• Construction expected to start in November 2010, pending SED approval, and continue until September 2012, with closeout by December 2012