Phase 4 - Long Beach High School [HS]

Project Phase Description:
• HS classroom and resource room addition construction, new media/music/TV studio construction, computer/auto repair room renovation, exterior concrete façade restoration, concrete sunscreen replacement, new athletic fields, tennis courts and pedestrian greenway reconstruction as well as demolition of Blackheath and relocation of the Lido portables
• HS guidance and administration reconstruction, science lab renovations, interior door and hardware replacement, restroom renovations, ventilation improvements, emergency lighting installation, security improvements, phone and public address system upgrades, ADA compliance upgrades as well as additional mechanical, electrical, and plumbing upgrades

Current Project Stage: Design Development [March – May 2010]

Subsequent Project stages:
• HS construction documents to be submitted to SED in November 2010, with SED approval anticipated in February 2011
• HS construction is expected to start in June 2011, and continue until September 2012, with closeout by December 2012