Phase 2A-1 - Lido Complex [LCX]

Project Phase Description:
• Lido Complex [LCX] partial roof replacement at Middle School

Current Project Stage: Construction [Dec 2009 – June 2010]
• Currently 70% complete and on schedule.

Subsequent Project Stage: Closeout [July – September 2010]

Phase 2A-2 - Long Beach High School [HS]

Project Phase Description:
• High School [HS] exterior exploratory concrete testing

Current Project Stage: Bidding [April – May 2010]
• Analyzing bids received on April 29th for recommendation to the Board at the May 18th meeting.
• conducting post-bid scope review with the lowest bidder, and checking qualifications and references

Subsequent Project Stage: Construction [June – August 2010]

Phase 2A-3 - Long Beach High School [HS]

Project Phase Description:
• High School [HS] minor mechanical, electrical, and plumbing upgrades.

Current Project Stage: Pre-construction [May – June 2010]
• Awaiting SED approval.

Subsequent Project Stage: Construction [June – August 2010]